Friday, January 22, 2010

Day 18 - 20 : Tiling works (Living hall)

The last major work : Tiling.


Cutting the tiles to the correct size for the sides


All done. Finally! This took them 3 days to complete the whole area.

Tuesday, January 19, 2010

Day 17 - Installing plaster ceiling

My back kitchen is done. So the last piece of work that the contractor needs to do is to tile my living hall. That can only be done if my plaster ceiling is up.


So, we've arranged for the plaster ceiling to be completed first.

Plastering my porch area.

Touching up on the plaster ceiling in the rooms

The most expensive area --> Dining area. These boxes cost a bomb even though there are only 6 of them. When lights are installed I'm sure it will look really comforting due to the concealed lighting.

Day 16 - Tiling Kitchen Slab

I thought the tiling of the kitchen slab was easy but it was not. This took them 1 whole day to complete.

I've also installed the back metal door.


Monday, January 18, 2010

Day 14 & 15 - Tiling Back extension

This is exciting. Tiling work for my wet kitchen.

Laying the wall tiles

All done now :D I like my wet kitchen.

Have added in the sink too.

Sunday, January 17, 2010

Day 13 - Renovation continues @ Front porch

Tiling the front porch area. This area was not tiled earlier as it meant for you to do some gardening. I'm giving gardening up. No one wants to do the weeding...


All done! Nice!

My new pillar is done too. :)

Tuesday, January 12, 2010

Day 12 - Kitchen Slab @ Wet kitchen

At first, they just put up some sort of wood planks for the shape of the slab





Then, they put the cement slab up.

Sunday, January 10, 2010

Day 11 - Back extension & Front gate

My back extension's floor is completed today. Will have to wait till it's dry to proceed with the next step which is tiling. Can't wait for my tiles to be up.




They are starting to build the new gate pillar.