Day 9 : Renovation : Front gate area

I'm extending the front gate. Before removing the existing pillar, the plumber came to relocate the water meter to the side.

Existing position of the water meter
Remove it

Whoaa.. A water fountain :)


Look at the quality of the water coming from the main pipe.. So Grosssss!!! Will definitely need a water filter.. ( Sighz.. that means more money being forked out.. :( )


Relocation completed. :)

Next... my front gate can be removed to make way of another hacking job.

The removal of the gate pillar work begins....

Thursday, December 24, 2009

TIles tiles tilesssss

My batch of tiles arrived today!

I bought White Horse Tiles for my Living hall.
Guocera tiles for my kitchen wall tiles.
Venus tiles for my kitchen floor tiles.
MML tiles for my porch.
The most expensive of all, tiles for my kitchen table top. RM30 per piece. (2x2)



Wednesday, December 23, 2009

Day 8 - Wiring works

No construction work today. Time allocated to my wiring man to do some wiring work





Tuesday, December 22, 2009

Day 7 - Renovation : Back Extension

They plastered all the inner walls of the back extension today.



Wednesday, December 16, 2009

Day 6 - Renovation : Back Extension & Hall

Many tasks running concurrently today..

One of it was to remove my existing tiles at the living hall. Poor tiles.. Goodbye farewell my friend! It's actually a waste.. :( Too bad...


Another worker was busy plastering the walls..

Plastering job is not easy. Took him a few hours just to do this wall.

Plumbing works.. My plumber came today to install some new piping for my back extension. Upon completion of the piping system, my contractor can continue with the floor works.

Day 5 - Renovation : Back Extension

The wiring works started today. The contracted needed to close up the ceiling. Therefore, all wiring has to be done first.



Once the wiring is done, it's time to close it up.


Day 4 - Renovation : Back Extension

They've completed the back structure. So the next thing they did was to knock down the wall between the dry kitchen and the wet kitchen. The new wet kitchen will be relocated to the new back extension.
As for the dry kitchen, it'll be bigger. :)

Friday, December 11, 2009

Day 3 - Renovation : Back Extension

All walls are done. So the next thing is to build the roof.








Wednesday, December 9, 2009

Day 2 - Renovation : Back Extension

On the second day, both the walls at the back is done. They've also laid some bricks on the existing middle wall to make it higher.






They removed some tiles too from my dry kitchen.